Gondola Construction

Construction on Sun Valley’s new Doppelmayr gondola from the base of River Run to Roundhouse is progressing. The new gondola cars have just arrived and preparation is underway for flying tower forms and concrete pours early next week!

UPDATED: The helicopter is finished for this phase. The top terminal photo was poured via truck and pumper, 15 towers were poured with the helicopter There are now 21 tower footings  in place.